Brandywine School District
Concord High School

- 224,000 s.f. renovation to existing high school
- Installation of 43,000 s.f. temporary modular classroom package
- Renovation
- Scope of Work:
- Upgraded MEP systems
- Upgraded athletic facilities
- New ceilings
- New lockers
- New science labs
- New elevator & shaft
- Cafeteria & library renovations
- Gymnasium floors & seating replaced
- New auditorium stage
- New acoustical treatments in music rooms
The renovations to Concord High School required extreme coordination among the Brandywine School District, Nason Construction, & the subcontractors to ensure student safety. All work was completed during non-learning hours with major demolition taking place over the summer.